BCWP Is calculating incorrectly

C

confused

Hi,

I have just rebaseliend my project and then click the 'analyse timescaled
data in excel' button to view BCWP, ACWP and BCWS.
My problem is that the BCWP is incorrect.For eacmple i have a task which is
1005 complete, ACWP = BCWS = £65, but BCWP = £17.33.
I have tried using %complete and physical %complete but with no success.
can anyone offer me any assistance please?

Many thanks
 
C

Chak

Hi,

I have just rebaseliend my project and then click the 'analyse timescaled
data in excel' button to view BCWP, ACWP and BCWS.
My problem is that the BCWP is incorrect.For eacmple i have a task which is
1005 complete, ACWP = BCWS = £65, but BCWP = £17.33.
I have tried using %complete and physical %complete but with no success.
can anyone offer me any assistance please?

Many thanks

Hello,

Do you set the Status Date? You have to set the status date to
perform the correct calculations from baseline info.

FYI: http://www.epmcentral.com/msproject/evprereq.php

Thanks
Chak
http://www.epmcentral.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top