I'm having some issues with my BCWP calculating in MSP 2007. I have entered
in tasks, fixed costs, resources, baselined the info, and entered status
information into the schedule. For some reason, the BCWP is not calculating
on some tasks while on other tasks it is. Does anyone know why this is? I
have the latest service pack installed.
thanks,
in tasks, fixed costs, resources, baselined the info, and entered status
information into the schedule. For some reason, the BCWP is not calculating
on some tasks while on other tasks it is. Does anyone know why this is? I
have the latest service pack installed.