confused
hi,
when I click 'analyse timescaled data in excel' the BCWP for completed tasks
is not equal to the BCWS. This is thne having a nock on effect to my CPI and
SPI.
It may be irrelevant, but although I am using project server, the project
plans were created some tme before we encouraged the use of individuals
submitting actuals via timesheets. therefore, the tasks in question have been
marked as complete byself in project server rather than by the individual
booking to the task.
Im using physical % complete in earned value analysis.
any help anyone can give would be much appreciated
when I click 'analyse timescaled data in excel' the BCWP for completed tasks
is not equal to the BCWS. This is thne having a nock on effect to my CPI and
SPI.
It may be irrelevant, but although I am using project server, the project
plans were created some tme before we encouraged the use of individuals
submitting actuals via timesheets. therefore, the tasks in question have been
marked as complete byself in project server rather than by the individual
booking to the task.
Im using physical % complete in earned value analysis.
any help anyone can give would be much appreciated