In order for Earned Value to be calculated you must also specifiy the Status
Date (Project menu, Project Information) to be used for the calculation.
Think of it as designating the reporting date within the project you want to
see the earned value figures for.
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Chris said:
thanks James,
I am using MS Project 2002.
I do have allocated resources with budgets, rates, durations etc. and a
baseline has been set and saved. I am entering actual hours used. I can
see BCWS, ACWP, SV, CV, EAC, BAC and VAC in the EV table, but for some
reason the BCWP values are all zero. The project is set to track physical %
complete independantly from actual hours spent against those budgeted. I
want to plot my S curve to see actual progress against planned both in time
and cost, but with BCWP at zero I'm sure I won't get the right answer - any
ideas?done by allocating resources, complete with their hours and hourly rate,
against the task, or directly entering a £ value in the task's Cost cell.
Doing this sets the BCWS.have to be really careful if you want to get meaningful values from the EV.
I assume that you are using MSP 2000. If so, the BCWP is calculated on the
basis of the % Complete of the DURATION of the task - and not on the % Work
Complete, as you would normally expect.the task as being 100%, without accounting for what really happened, over
whatever period, then you will get a "perfect" EV curve - which isn't really
much help - especially if it isn't the reality.over two years ago by others. I can view the eanred value table ok, but the
BCWP column retunrs zero values against all activites - does anyone know
why? I expect it's some simple setting I've missed.