Bcws $0.00?

A

anilksk

Hello!

Can some one please help me with BCWS? Why is BCWS $0.00? the same i
true for BCWP, ACWP I have setup the resources and cost/baseline, EA
and BAC look good.

Why is BCWS $0.00?

Thank
 
G

Gérard Ducouret

Hello Anilksk,

Did you set the Status Date : Project / Project information ?

Gérard Ducouret
 
J

Jim Aksel

To add to Gerard's post: BCWP and ACWP will remain at $0.00 until you claim a
percent complete. If you have Actuals set to manual, you will need to enter
them manually.

BCWP and ACWP will only post in the Baseline period unless you enter an
[Actual Start] and/or [Actual Finish] date. Project assumes [Actual
Start/Finish] = [Start/Finish] unless you tell it otherwise in the [Actual
Start/Finish] columns.
--
If this post was helpful, please consider rating it.

Jim
It's software; it's not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 