G
ghostme
I really need to understand Budgeted Cost of Work Schedule and the way it
works in Project Server 2007.
Now if this what BCWS means - If you are expected to spend $100.00 on a
task, when the schedule for the task is showing that it should be 40%
complete, then the BCWS would amount to $40.00.
Simply put, the BCWS is the estimated cost of what you thought it would
take to get the task or project done up to a certain status date.
However, in Project Server if a project is 40% complete, the BCWS doesn't
change it still assume the cost of the Baseline cost.
Please 'am I missing something?
works in Project Server 2007.
Now if this what BCWS means - If you are expected to spend $100.00 on a
task, when the schedule for the task is showing that it should be 40%
complete, then the BCWS would amount to $40.00.
Simply put, the BCWS is the estimated cost of what you thought it would
take to get the task or project done up to a certain status date.
However, in Project Server if a project is 40% complete, the BCWS doesn't
change it still assume the cost of the Baseline cost.
Please 'am I missing something?