T
TinkerBell
We perform hardware and software maintenance actions, and have to constantly
add tasks ranging from weeks to years to the overall plan. As such, some of
the tasks are always going to be complete and some not. The problem we are
having is that after adding tasks to a plan and saving them to the baseline,
the baseline work skews away from the BCWS, and at the end of the baselined
plan, the two values do not end up with the same.
Any help in understanding this skew would be appreciated.
Thanks.
add tasks ranging from weeks to years to the overall plan. As such, some of
the tasks are always going to be complete and some not. The problem we are
having is that after adding tasks to a plan and saving them to the baseline,
the baseline work skews away from the BCWS, and at the end of the baselined
plan, the two values do not end up with the same.
Any help in understanding this skew would be appreciated.
Thanks.