M
Michael
I don't understand the BCWS and the BCWP results when the task is 100%
complete.
If a task takes 5 days, and has one resource (at $100 / day) assigned
to it.
The Budgeted Cost of Work Scheduled would be $500
The task is complete, and the resource worked 6 days on it, so the
Budgeted Cost of Work Complete should be $500
And the Actual Cost of Work Performed should be $600.
The actual work is there... 6 days.
So why does MSProject say BCWC = 0?
complete.
If a task takes 5 days, and has one resource (at $100 / day) assigned
to it.
The Budgeted Cost of Work Scheduled would be $500
The task is complete, and the resource worked 6 days on it, so the
Budgeted Cost of Work Complete should be $500
And the Actual Cost of Work Performed should be $600.
The actual work is there... 6 days.
So why does MSProject say BCWC = 0?