B
bauer172uw
Our organization noticed a property of how BCWS is calculated. The issue
arrises when you have a summary task, baseline, and then remove subtasks
post-baseline. Now looking to a time down the road (now) with the status
date set to the current date (also beyond the baseline finish of all
subtasks), the BCWS for the summary task still accounts for the cost of the
tasks that were removed.
So, in my sample project I created this very instance. I made 5 subtasks,
each costing $100. I baselined. Then I removed one of the subtasks. After
updating the Physical % Complete AND the % Work Complete fields my summary
tasks EV is as follows:
BCWS: $500
BCWP: $400
ACWP: $400
It should be noted that the summary task's '% Work Complete'=100% while
'Physical % Complete'=80%. We have set both fields to have 100% for each
subtask. Why is it that these are not equal then?
So BCWP and ACWP seem correct. When looking at BCWS I wonder why is BCWS
not $400. This $500 indicates that somehow the BCWS for the summary task is
coupled to the task that was removed. OK, I could buy that, but how? I
thought it may be coupled via 'Baseline Cost' or 'Baseline Work' but changing
these fields did not alter the BCWP. So how is BCWS attached to this removed
task.
My concern is that, after our baseline, every time we remove a task we will
need to rebaseline it's summay task (recursively all the way up the project).
Does anyone have a solution or best practices method for this?
Note: I truely believe that the status date, EV calculation method, baseline
used for calc., and autocalculate are set correctly and are not the problem.
Thank You for any help.
Mike
arrises when you have a summary task, baseline, and then remove subtasks
post-baseline. Now looking to a time down the road (now) with the status
date set to the current date (also beyond the baseline finish of all
subtasks), the BCWS for the summary task still accounts for the cost of the
tasks that were removed.
So, in my sample project I created this very instance. I made 5 subtasks,
each costing $100. I baselined. Then I removed one of the subtasks. After
updating the Physical % Complete AND the % Work Complete fields my summary
tasks EV is as follows:
BCWS: $500
BCWP: $400
ACWP: $400
It should be noted that the summary task's '% Work Complete'=100% while
'Physical % Complete'=80%. We have set both fields to have 100% for each
subtask. Why is it that these are not equal then?
So BCWP and ACWP seem correct. When looking at BCWS I wonder why is BCWS
not $400. This $500 indicates that somehow the BCWS for the summary task is
coupled to the task that was removed. OK, I could buy that, but how? I
thought it may be coupled via 'Baseline Cost' or 'Baseline Work' but changing
these fields did not alter the BCWP. So how is BCWS attached to this removed
task.
My concern is that, after our baseline, every time we remove a task we will
need to rebaseline it's summay task (recursively all the way up the project).
Does anyone have a solution or best practices method for this?
Note: I truely believe that the status date, EV calculation method, baseline
used for calc., and autocalculate are set correctly and are not the problem.
Thank You for any help.
Mike