N
nde
Hi,
I do have an issue with the BCWS calculation that is equal to 0 evevn if the
project as been baselined correctly. This apparently comes from the fact that
the status date is NA.
The questions are the folloeing:
1- The BCWS is calculated up to the date defined in the Status date Field ?
2- If yes, How do I set this field to nbe automaticaly set to today's date ?
Thanks,
Nde
I do have an issue with the BCWS calculation that is equal to 0 evevn if the
project as been baselined correctly. This apparently comes from the fact that
the status date is NA.
The questions are the folloeing:
1- The BCWS is calculated up to the date defined in the Status date Field ?
2- If yes, How do I set this field to nbe automaticaly set to today's date ?
Thanks,
Nde