I need help with figuring out why the BCWS is not calculating. This appears
to be happening with tasks that I added after the project was baselined. The
answer to the obvious question is did I baseline these tasks that were added,
YES I did.
These tasks have an assigned resource with a cost value. The baseline
duration and cost fields contain data.
When I update the % work complete, BCWP will update, however the BCWS is not
updating. I realize that the BCWS should already have a value before I start
updating the % Work complete.
Does anyon have suggestions?
Don
to be happening with tasks that I added after the project was baselined. The
answer to the obvious question is did I baseline these tasks that were added,
YES I did.
These tasks have an assigned resource with a cost value. The baseline
duration and cost fields contain data.
When I update the % work complete, BCWP will update, however the BCWS is not
updating. I realize that the BCWS should already have a value before I start
updating the % Work complete.
Does anyon have suggestions?
Don