Lucas Soler
My plan is showing a BCWS of $0 when there should have been a value. The
status date was set later than the baseline finish of the task to make sure
that all of the work for that task would be captured in the BCWS (BCWS should
be equal to Baseline Cost).
When I went to the task usage view, I noticed that each resource had a
correct BCWS value, but this value was not rolling up to the yellow task
line.
Because it was not rolling up, the BCWS for the task is showing $0.
Does anybody know what may be causing this?
Thank you.
status date was set later than the baseline finish of the task to make sure
that all of the work for that task would be captured in the BCWS (BCWS should
be equal to Baseline Cost).
When I went to the task usage view, I noticed that each resource had a
correct BCWS value, but this value was not rolling up to the yellow task
line.
Because it was not rolling up, the BCWS for the task is showing $0.
Does anybody know what may be causing this?
Thank you.