LearnerMSP
Hi,
I'm having issues with BCWS. I thought that by setting Project Status Date
to the last date of the project and exporting BCWS values to excel I was
going to be able to have a projected S-curve for the whole timeline of the
project, that would serve as a "frozen" baseline to track project performance
as my project advances. However, when I update project progress and change
the status date to an earlier date in order to see how the project is
performing I notice that BCWS values for the same dates change, how is that
possible? How can I obtain fixed time-phased baseline values that do not
change upon "status date" ??? please help!! Thank you!!!
I'm having issues with BCWS. I thought that by setting Project Status Date
to the last date of the project and exporting BCWS values to excel I was
going to be able to have a projected S-curve for the whole timeline of the
project, that would serve as a "frozen" baseline to track project performance
as my project advances. However, when I update project progress and change
the status date to an earlier date in order to see how the project is
performing I notice that BCWS values for the same dates change, how is that
possible? How can I obtain fixed time-phased baseline values that do not
change upon "status date" ??? please help!! Thank you!!!