E
Elvis
We do not load cost in our schedules based on legal and company proprietary
rules. Instead we use a BHWS and BHWP in the scheduling group. Of course
those hours are costed in a financial system which mirrors the work spread in
MS Projects timephased view.
The problem is, as an analyst i'd like to have visible, next to Projects %
Work Completed, a field that displays the hours that should have been
completed by the current date (or status date); Basically a BHWP or BHWS
field.
Since at the detail tasks our hours are level loaded, I can write the
formula to provide the data I am looking for but I am concerned at the
summary level the formula does not provide an accurate number since on the
summary level the hours are not level loaded as a result of timescale spreads
overlapping, etc.
Any help on getting the summary number for this BHWS concept is greatly
appreciated.
rules. Instead we use a BHWS and BHWP in the scheduling group. Of course
those hours are costed in a financial system which mirrors the work spread in
MS Projects timephased view.
The problem is, as an analyst i'd like to have visible, next to Projects %
Work Completed, a field that displays the hours that should have been
completed by the current date (or status date); Basically a BHWP or BHWS
field.
Since at the detail tasks our hours are level loaded, I can write the
formula to provide the data I am looking for but I am concerned at the
summary level the formula does not provide an accurate number since on the
summary level the hours are not level loaded as a result of timescale spreads
overlapping, etc.
Any help on getting the summary number for this BHWS concept is greatly
appreciated.