Become the manager of these assignments issue

A

Adam Bennett

Hello
We've been running into a problem recently with changing ownership on a few
different project plans. We've changed ownership on a few plans and after
the PM republishes the plan while checking the "become the manager of these
assignments" checkbox, some (but not all) updates are still going to the
previous manager. We've made sure that all updates are approved by the
previous manager before republishing and when republishing that the "entire
plan" value is selected. Does anyone know why this may be happening and how
to change it?

Any help would be appreciated

Thanks!
Adam
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question