We've been running into a problem recently with changing ownership on a few
different project plans. We've changed ownership on a few plans and after
the PM republishes the plan while checking the "become the manager of these
assignments" checkbox, some (but not all) updates are still going to the
previous manager. We've made sure that all updates are approved by the
previous manager before republishing and when republishing that the "entire
plan" value is selected. Does anyone know why this may be happening and how
to change it?
Any help would be appreciated
Thanks!
Adam
We've been running into a problem recently with changing ownership on a few
different project plans. We've changed ownership on a few plans and after
the PM republishes the plan while checking the "become the manager of these
assignments" checkbox, some (but not all) updates are still going to the
previous manager. We've made sure that all updates are approved by the
previous manager before republishing and when republishing that the "entire
plan" value is selected. Does anyone know why this may be happening and how
to change it?
Any help would be appreciated
Thanks!
Adam