One advantage from having the individual projects resident and managed in
their individual files with a consolidation file displaying the "big
picture" is it makes indentification and managment of each project's
critical path easier. A "project" is defined as the set of activities that
produce a unique product or result. When I look at a project's file, I like
to see the activities that go into that result and that result only - no
other projects, no "overhead", no administrative activities thyat do not
contribute directly to the project deliverable.
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Conrad Santiago said:
Thanks for the input, Rob.
Now, you have me wondering. Our PM files range from 200 to 1000 tasks.
Each project ranges from 20 tasks to 75 tasks. I'm surprised I'm not having
more problems. I'd be interested to hear your experiences that led you to
these guidelines.
Are there other benefits? With one project on one file, can I do things
with it that I can't do when there are multiple projects in one file?
One example (which I couldn't figure out how to do anyway) was to give the
task bars of a project a different color, so that I can distinguish them in
a balance view. Can you give settings to a project if it is in one file
that will show up in other views?
----- Rob Schneider wrote: -----
I guess it all depends on how the PM's handle their own portfolio of a
dozen projects and whether they prefer consolidation or segregation of
files.
You ---+-- PM1
| +--------+--- Project 1
+ +--- Project 2
+ +--- Project 3
+ +--- Etc
+-- PM2
+ +--------+--- Project 13
| +--- Project 14
| +--- Etc.
+-- Etc.
I would think that each PM would find their own benefits of using
individual files for individual projects ... all depends on how many
tasks for each file. Everyone has their own preference. I personally
like (for many reasons--some logical and others just opinion/experience)
to see no more than 100-300 tasks per file. If these projects are
modeled by 10 tasks, then consolidation probably easier. If projects
more than this, then even having multiple files per project is not out
of the question.
The good news is that Project can handle all these roll ups like this
relatively easily. It's all helped by using shared resource files which
I hope you are using.
Hope this is useful to you. Let us know.
rms
come from our six project managers. Each of them has one file where they
manage their projects under summary tasks. In all, there are about 80
projects.