J
jp
Hi,
My question is the following:
I have a project whose tasks have been estimated in hours by the technical
team.
The project team is supposed to only be available 50% of their time.
And once the project started the task duration is in days sometimes weeks.
What is the best way to set these tasks?
And what task type should be used?
Can these tasks have a mixture of types (Fixed Duration, Fixed Units, Fixed
Work)
Thanks.
-jp
My question is the following:
I have a project whose tasks have been estimated in hours by the technical
team.
The project team is supposed to only be available 50% of their time.
And once the project started the task duration is in days sometimes weeks.
What is the best way to set these tasks?
And what task type should be used?
Can these tasks have a mixture of types (Fixed Duration, Fixed Units, Fixed
Work)
Thanks.
-jp