B
Bill Cole
Is more detail or less detail better in a published project?
I am involved in the initial rollout of Project Server / PWA at my
organization. We have used Project Server for years in the scheduling of
projects but had never tracked the progress electronically once the project
started. Of course we want to get buy in from our engineering staff to
apply their hours via PWA weekly and also properly enter the work remaining
so that Project can give us the best possible prediction of when the project
will be complete. This level of detailed project tracking is something new
for our company's culture so the issue of buy-in from the staff is
important.
We have a fairly detailed development schedule consisting of about 200
activities, ranging in duration from 1 day to 2 weeks. This is a
development team of about 9 resources on a development project of about 8
months.
My question is what is the best level of granularity to publish in to
Project Server for the best balance between detailed tracking and user
buy-in on a first project? My initial thought was to publish the detailed
schedule as is and track every single leg, this would give the best possible
results in tracking the project end date. However, some feedback I have
gotten from various members of the team indicate that it may be better to
compromise on this (i.e. not overwhelm users new to PWA), and only
publish/track the schedule to the level of the 'rollup tasks', i.e. maybe 40
major task groupings instead of the whole. These would be easier for users
new to PWA to deal with, especially for a first project.
From a project post-mortem point of view, I am fine with this, I only intend
to compare 'estimated hours' vs. 'actual hours' on a high level feature
basis at the end of the project.
But I am concerned that if we are tracking at a less granular level, that
the project finish date will be less accurate as development goes along, as
it is tougher for people to realize that
a 6 week leg has fallen behind than a 1 week leg.
Any advice from those who have successfully used PWA for tracking projects
and then analyzing the results post-project? What is the best practice
here? As much detail as you can
get, or only track high level tasks?
Thanks,
Bill
I am involved in the initial rollout of Project Server / PWA at my
organization. We have used Project Server for years in the scheduling of
projects but had never tracked the progress electronically once the project
started. Of course we want to get buy in from our engineering staff to
apply their hours via PWA weekly and also properly enter the work remaining
so that Project can give us the best possible prediction of when the project
will be complete. This level of detailed project tracking is something new
for our company's culture so the issue of buy-in from the staff is
important.
We have a fairly detailed development schedule consisting of about 200
activities, ranging in duration from 1 day to 2 weeks. This is a
development team of about 9 resources on a development project of about 8
months.
My question is what is the best level of granularity to publish in to
Project Server for the best balance between detailed tracking and user
buy-in on a first project? My initial thought was to publish the detailed
schedule as is and track every single leg, this would give the best possible
results in tracking the project end date. However, some feedback I have
gotten from various members of the team indicate that it may be better to
compromise on this (i.e. not overwhelm users new to PWA), and only
publish/track the schedule to the level of the 'rollup tasks', i.e. maybe 40
major task groupings instead of the whole. These would be easier for users
new to PWA to deal with, especially for a first project.
From a project post-mortem point of view, I am fine with this, I only intend
to compare 'estimated hours' vs. 'actual hours' on a high level feature
basis at the end of the project.
But I am concerned that if we are tracking at a less granular level, that
the project finish date will be less accurate as development goes along, as
it is tougher for people to realize that
a 6 week leg has fallen behind than a 1 week leg.
Any advice from those who have successfully used PWA for tracking projects
and then analyzing the results post-project? What is the best practice
here? As much detail as you can
get, or only track high level tasks?
Thanks,
Bill