A
ant1983
Hi,
So I'm quite new to MS Projects and trying to understand something so any
help would be much appreciated:
I update my plan on a weekly basis after receiving my updates (progress on
tasks) from the Project Manager.
I capture these updates every two weeks so lets say on the 13th and 27th of
every month.
Now what i would like to do is include a screenshot of my plan in my
bi-weekly report. (I know how to do this; think you just click the little
camera button and then paste this in word or whatever.)
The challenge is to show what the situation should have been (as per the
planned dates) vs what the reality is (actual dates).
Now in terms of best practise or the RIGHT way of doing this, here are my
questions:
1 - Let's say a task called UAT was suppose to start on 1 Jan 09 and end on
10 Jan 09 but instead it ended on 13 Jan 09 - Is the right way to change the
end date to 13 Jan 09 or to increase the duration of the task by 3 days?
2 - Also, I'd like my report to reflect as described above (planned vs
actual): I've read a bit about baselines so im assuming this is what i want
to do - My question is: How do i show this baselines but only milestones.
3 - Last question: When is the best time to save a baseline? Before or
after i update my plan?
Cheeeers!
Wayne
So I'm quite new to MS Projects and trying to understand something so any
help would be much appreciated:
I update my plan on a weekly basis after receiving my updates (progress on
tasks) from the Project Manager.
I capture these updates every two weeks so lets say on the 13th and 27th of
every month.
Now what i would like to do is include a screenshot of my plan in my
bi-weekly report. (I know how to do this; think you just click the little
camera button and then paste this in word or whatever.)
The challenge is to show what the situation should have been (as per the
planned dates) vs what the reality is (actual dates).
Now in terms of best practise or the RIGHT way of doing this, here are my
questions:
1 - Let's say a task called UAT was suppose to start on 1 Jan 09 and end on
10 Jan 09 but instead it ended on 13 Jan 09 - Is the right way to change the
end date to 13 Jan 09 or to increase the duration of the task by 3 days?
2 - Also, I'd like my report to reflect as described above (planned vs
actual): I've read a bit about baselines so im assuming this is what i want
to do - My question is: How do i show this baselines but only milestones.
3 - Last question: When is the best time to save a baseline? Before or
after i update my plan?
Cheeeers!
Wayne