M
Michael M
Hi All,
I'm fairly new to project server 2007, and would like to know what the best
way to close a project off. Currently our project managers are closing off
projects in various ways.
What I would like is
1. To disable the ability for users to put additional time to any tasks for
the project. I have used "Close task to update" and this seems to work ok
except the users can still see the tasks in the "My Tasks" area.
2. Users not to be able to see the tasks in the "My Tasks". Essentially i
want to minimise the amount of Project and Tasks the users can see, even if
they have the "Show Only Current Tasks" deselected.
Thanks
Michael
I'm fairly new to project server 2007, and would like to know what the best
way to close a project off. Currently our project managers are closing off
projects in various ways.
What I would like is
1. To disable the ability for users to put additional time to any tasks for
the project. I have used "Close task to update" and this seems to work ok
except the users can still see the tasks in the "My Tasks" area.
2. Users not to be able to see the tasks in the "My Tasks". Essentially i
want to minimise the amount of Project and Tasks the users can see, even if
they have the "Show Only Current Tasks" deselected.
Thanks
Michael