G
Gary Furash
I was hoping to get some ideas on best practices for
documenting risk buffers and non-productive time in MS
Project.
For example, let's say task "X" is estimated to take 3
days, if the resource could focus on it exclusively and
things went the way we expected. However:
1. given the fact that they probably can't focus it on it
exclusively (emergencies, meetings, etc.), they can
really only work at 70% of capacity;
2. if one of the accepted risks becomes realized, it
could take longer (say an additional week).
You could make the task longer, reduce the resource
availability, etc.
Given that we do not really track people to the hour here
(we don't care about that level of detail), what are some
best practices.
documenting risk buffers and non-productive time in MS
Project.
For example, let's say task "X" is estimated to take 3
days, if the resource could focus on it exclusively and
things went the way we expected. However:
1. given the fact that they probably can't focus it on it
exclusively (emergencies, meetings, etc.), they can
really only work at 70% of capacity;
2. if one of the accepted risks becomes realized, it
could take longer (say an additional week).
You could make the task longer, reduce the resource
availability, etc.
Given that we do not really track people to the hour here
(we don't care about that level of detail), what are some
best practices.