A
Angela
I need help, best practices and any troubleshooting tips for task tracking
I'm using MOSS 2007 with Project Server 2007 SP1 & SQL 2005. Our tracking
method is % of Work Complete, all projects are forced to use this method.
I've republished all projects to force this change.
I want to turn off timesheets and approval of task updates.
We need automatic approval of any task update.
We want project team members to update the progress of each task under PWA
--> My Tasks, which automatically update project plan information in Project
Center
Can anyone give me the steps to set this up correctly...I've missed
something...I still have to approve all updates and updates don't show up in
project center without republishing the entire project.
I need a simple method of tracking progress on active, published projects.
Please help
Thank you, Angela
I'm using MOSS 2007 with Project Server 2007 SP1 & SQL 2005. Our tracking
method is % of Work Complete, all projects are forced to use this method.
I've republished all projects to force this change.
I want to turn off timesheets and approval of task updates.
We need automatic approval of any task update.
We want project team members to update the progress of each task under PWA
--> My Tasks, which automatically update project plan information in Project
Center
Can anyone give me the steps to set this up correctly...I've missed
something...I still have to approve all updates and updates don't show up in
project center without republishing the entire project.
I need a simple method of tracking progress on active, published projects.
Please help
Thank you, Angela