G
Gary Furash
I was hoping to get any best practices for the creation
of Buffers (Contingency, etc.). That is, if a given task
or summary task (I have both situations):
- is likely to take X;
- but could take much more if something goes badly wrong,
or some possible, accepted risk occurs; and
- I have some idea how much extra it could take.
Things I've done before:
- Extended the expected duration of the task with notes
that it could take less.
- Created an associated buffer task, clearly identified
as such.
of Buffers (Contingency, etc.). That is, if a given task
or summary task (I have both situations):
- is likely to take X;
- but could take much more if something goes badly wrong,
or some possible, accepted risk occurs; and
- I have some idea how much extra it could take.
Things I've done before:
- Extended the expected duration of the task with notes
that it could take less.
- Created an associated buffer task, clearly identified
as such.