R
rgille
I have a task that requires 1000 hours of work. I have assigned 7 people
working 100% (full-time) to the task to finish it by the deadline. Actual
work done the first week has lagged, so I will need to assign more people to
the task to finish by the deadline. What is the best way to assign more
resources to a task that already has work done on it? I tried adding more
resources to the task, but that added the additional resources from the start
date of the task, which isn’t accurate. What is the best way to set up tasks
so I can easily add more resources later if needed? Thank you.
working 100% (full-time) to the task to finish it by the deadline. Actual
work done the first week has lagged, so I will need to assign more people to
the task to finish by the deadline. What is the best way to assign more
resources to a task that already has work done on it? I tried adding more
resources to the task, but that added the additional resources from the start
date of the task, which isn’t accurate. What is the best way to set up tasks
so I can easily add more resources later if needed? Thank you.