L
lynne baker
Hi all
Project Pro 2002
Server 2002
PWA
I'm sure this is such a basic issue, but some guidance from the
experts would be very much appreciated.
I have almost 300 tasks and about 8 resources.
I would like to allocate tasks to these resources such that the
application calculates what the percentage allocation is.
At the moment we're doing it like this
Create a task
Allocate a resource
Decide what percentage of the resource's time it might take
decide how long it's going to take and enter it into duration
decide how many hours effort is going to be required and enter it into
work.
Something tells me one of those steps is superfluous...
And my resources are all horribly overallocated too!
Ideally, what I'd like to do is keep the work the same, alter the
duration to accommodate the amount of work, and calculate the
percentage allocation automatically.
Again, something tells me I'm asking for the moon!
Many thanks for your help!
Project Pro 2002
Server 2002
PWA
I'm sure this is such a basic issue, but some guidance from the
experts would be very much appreciated.
I have almost 300 tasks and about 8 resources.
I would like to allocate tasks to these resources such that the
application calculates what the percentage allocation is.
At the moment we're doing it like this
Create a task
Allocate a resource
Decide what percentage of the resource's time it might take
decide how long it's going to take and enter it into duration
decide how many hours effort is going to be required and enter it into
work.
Something tells me one of those steps is superfluous...
And my resources are all horribly overallocated too!
Ideally, what I'd like to do is keep the work the same, alter the
duration to accommodate the amount of work, and calculate the
percentage allocation automatically.
Again, something tells me I'm asking for the moon!
Many thanks for your help!