K
Kay
Dear all,
I have a question, what the best way to enter part time resources is.
Situation:
I have one resource who is working 80% and we can be sure he never
works on wednesdays.
He has two major duties which are split 50% and 30%.
I considered the following:
a) I enter him as 100% and use the resource calendar to mark the
wednesdays as non-working time
b) I enter him as 80% (feels more right), leave the resource calendar
untouched
c) I enter him as 80% and mark his absence on wednesdays in the
resource calendar.
So I entered one of his 50% tasks (10 dayw working time, fixed work)
under setup a:
It calculates 20 days duration
Setup b:
It also calculates 20 days duration but shifts the end date a week to
the front
Setup c:
It calculates 20 days duration and puts the delivery date on the same
date as a.
So what is the right way doing it?
Regards
Kay
I have a question, what the best way to enter part time resources is.
Situation:
I have one resource who is working 80% and we can be sure he never
works on wednesdays.
He has two major duties which are split 50% and 30%.
I considered the following:
a) I enter him as 100% and use the resource calendar to mark the
wednesdays as non-working time
b) I enter him as 80% (feels more right), leave the resource calendar
untouched
c) I enter him as 80% and mark his absence on wednesdays in the
resource calendar.
So I entered one of his 50% tasks (10 dayw working time, fixed work)
under setup a:
It calculates 20 days duration
Setup b:
It also calculates 20 days duration but shifts the end date a week to
the front
Setup c:
It calculates 20 days duration and puts the delivery date on the same
date as a.
So what is the right way doing it?
Regards
Kay