V
Vit
My company use an Estimated Computer based program to generate a cost
estimation of the project… (to allocate a budget for a cost/finance
scope…)
The output of the Estimated Program is an excel file with a quite good
WBS, work hours ad a quite good estimation of the duration…
Which is the best way to use the excel file??? Copy and paste as a
link or just copy and paste???
I have this question because I will use an excel file to do some
analysis and to print out a sort of time sheet for the work schedule….
Is possible to link excel and project in both ways??? Not with only a
“preferred way”??? (copy and paste link in both side so when I will
update in excel I will see the new info in project and vice versa…..)
The problem is that for Project Management Issues, the original Excel
file will be “the start”, and the plan will be a little different….
This is my idea:
Copy and paste from the estimated excel file to the WBS, work, and
duration
Generate the plan
Save baseline
Generate a new excel file and copy and paste link from the project to
excel
For example I will use excel to track the daily physical
“production” (think about at task as “drilling” where in project I
will have the total meters, the target production per day (custom
field -> meters/duration) and the actual production)… in this case I
will track the daily production in excel (because in Project I can
track on a calendar base only the work….) and link the into to project
(copy and past link)…
In this case, Is it possible to save the excel file in the workspace?
(I’m working on an EPM 2007 solution…)
I will appreciate every suggestion…
Thank you so much…
Vit
estimation of the project… (to allocate a budget for a cost/finance
scope…)
The output of the Estimated Program is an excel file with a quite good
WBS, work hours ad a quite good estimation of the duration…
Which is the best way to use the excel file??? Copy and paste as a
link or just copy and paste???
I have this question because I will use an excel file to do some
analysis and to print out a sort of time sheet for the work schedule….
Is possible to link excel and project in both ways??? Not with only a
“preferred way”??? (copy and paste link in both side so when I will
update in excel I will see the new info in project and vice versa…..)
The problem is that for Project Management Issues, the original Excel
file will be “the start”, and the plan will be a little different….
This is my idea:
Copy and paste from the estimated excel file to the WBS, work, and
duration
Generate the plan
Save baseline
Generate a new excel file and copy and paste link from the project to
excel
For example I will use excel to track the daily physical
“production” (think about at task as “drilling” where in project I
will have the total meters, the target production per day (custom
field -> meters/duration) and the actual production)… in this case I
will track the daily production in excel (because in Project I can
track on a calendar base only the work….) and link the into to project
(copy and past link)…
In this case, Is it possible to save the excel file in the workspace?
(I’m working on an EPM 2007 solution…)
I will appreciate every suggestion…
Thank you so much…
Vit