P
Pete Barry
Hi all,
I am a bit disappointed about the MS Project leveling mechanism. It seems
that MS Project cannot automatically balance the work time of a resource
among multiple tasks.
So here is my question: How do you handle the following scenario in your
daily work: The developer Jim is assigned to a software development task
called "Parser Implementation" which starts now and requires a fixed work
amount of 100 hours. But it is also assigned to a task "Coaching of Team
member Bob" with 10% of his working time for the next 2 weeks.
How do you best cope with these two tasks in MS Project? If you give
"Coaching of Team member Bob" the higher priority and assign Jim to 100% to
the task "Parser Implementation", the automatic leveling facility gives Jim
only a work load of 10% (from "Coaching of Team member Bob") for the next two
weeks because it does not let him start working on "Parser Implementation".
If on the other hand I only assign Jim with 90% to "Parser Implementation",
the leveling facility lets Jim start immediately and work in parallel to the
task "Coaching of Team member Bob" but gives him only a work load of 90%
after "Coaching of Team member Bob" was finished.
How do you handle a constellation like this best? Simply do all the leveling
manually? This can be quite a pain in the a... and become virtually
impossible if the project gets more complex.
Thanks in advance,
--- Pete Barry
I am a bit disappointed about the MS Project leveling mechanism. It seems
that MS Project cannot automatically balance the work time of a resource
among multiple tasks.
So here is my question: How do you handle the following scenario in your
daily work: The developer Jim is assigned to a software development task
called "Parser Implementation" which starts now and requires a fixed work
amount of 100 hours. But it is also assigned to a task "Coaching of Team
member Bob" with 10% of his working time for the next 2 weeks.
How do you best cope with these two tasks in MS Project? If you give
"Coaching of Team member Bob" the higher priority and assign Jim to 100% to
the task "Parser Implementation", the automatic leveling facility gives Jim
only a work load of 10% (from "Coaching of Team member Bob") for the next two
weeks because it does not let him start working on "Parser Implementation".
If on the other hand I only assign Jim with 90% to "Parser Implementation",
the leveling facility lets Jim start immediately and work in parallel to the
task "Coaching of Team member Bob" but gives him only a work load of 90%
after "Coaching of Team member Bob" was finished.
How do you handle a constellation like this best? Simply do all the leveling
manually? This can be quite a pain in the a... and become virtually
impossible if the project gets more complex.
Thanks in advance,
--- Pete Barry