S
SMAMurrayPM
In our environment, successor tasks should never start until a predecessor
task is complete. We have a scenario where a predecessor task may not be
complete by the time the successor task's start date.
Is there a way to have Project automatically move a task when there is no
time reported for it on a day?
For example: I work on Task A on Monday and report 7 hours. On Tuesday, I'm
pulled off to something else. I don't report time on Task A. Can project
automatically split my task to resume on Wednesday?
Ultimately it would be nice for no notifications to go out to my "successor"
resources until a predecessor task is %100 complete. Right now we solve that
kind of thing with our support ticket tracking database. It handles our
workflows without dates. The problem with that ticket tracking flow is that
it is serial. I need multiple people to start work upon completion of a
predecessor task.
Thanks for your help!
task is complete. We have a scenario where a predecessor task may not be
complete by the time the successor task's start date.
Is there a way to have Project automatically move a task when there is no
time reported for it on a day?
For example: I work on Task A on Monday and report 7 hours. On Tuesday, I'm
pulled off to something else. I don't report time on Task A. Can project
automatically split my task to resume on Wednesday?
Ultimately it would be nice for no notifications to go out to my "successor"
resources until a predecessor task is %100 complete. Right now we solve that
kind of thing with our support ticket tracking database. It handles our
workflows without dates. The problem with that ticket tracking flow is that
it is serial. I need multiple people to start work upon completion of a
predecessor task.
Thanks for your help!