P
Pat
Right now I use a general materials resource (called "materials") to assign
material costs to a task. I have the rate set to $1/unit so the units
entered is the cost estimate of the materials needed for the task. So far
that approach has worked well, especially for initial project planning.
What I'd like to do now though is link these material costs to an itemized
list of the actual materials needed for the task. For example, I may have a
task, "Construct motor stator" that requires the following material items:
1000' of 20 guage wire: $100
10 lbs stamped laminations: $150
10' of slot liner: $20
electrical varnish: $30
-------------------------------
Total = $300
Right now I'm using an Excel spreadsheet to track these items and hand
updating the totals (in the materials resource units) in the project plan.
However, that is rather tedious to do (to say the least), and so was
wondering if anyone knew of a better way to do this? It would be nice to
have all this information together in the project plan (rather than having
it in a separate spreadsheet) but the only way I know to do this now is to
list each individual material item in the Resource Sheet, which would make
the resource sheet very, very long. Besides, most of these materials are
only used for one task. Any suggestions?
Thanks for the help.
Pat
material costs to a task. I have the rate set to $1/unit so the units
entered is the cost estimate of the materials needed for the task. So far
that approach has worked well, especially for initial project planning.
What I'd like to do now though is link these material costs to an itemized
list of the actual materials needed for the task. For example, I may have a
task, "Construct motor stator" that requires the following material items:
1000' of 20 guage wire: $100
10 lbs stamped laminations: $150
10' of slot liner: $20
electrical varnish: $30
-------------------------------
Total = $300
Right now I'm using an Excel spreadsheet to track these items and hand
updating the totals (in the materials resource units) in the project plan.
However, that is rather tedious to do (to say the least), and so was
wondering if anyone knew of a better way to do this? It would be nice to
have all this information together in the project plan (rather than having
it in a separate spreadsheet) but the only way I know to do this now is to
list each individual material item in the Resource Sheet, which would make
the resource sheet very, very long. Besides, most of these materials are
only used for one task. Any suggestions?
Thanks for the help.
Pat