Billable and Non-billable time

B

Bentley-PSO

I saw in a demo that a resource can log time to a billable or non-billable
task via the Project Server timesheet. How is this accomplished? Outline
codes? How does it show up on the time sheet? Please explain.

Thanks
 
D

Dale Howard [MVP]

Bentley --

Perhaps you can tell us where you saw this demo since there is no default
method within Project Server to do what you describe. Let us know.
 
M

Marc Soester

Hi Bentley,

Could it be that you have seen a Project Server 2007 presentation? Project
Server 2007 allows you to log billable and non billable time, but this
release will not come out for another couple of month ( between Nov 2006 and
Jan 2007 ).

You are not able to track billable and non billable time within the current
release which is Project Server 2003
Hope this helps
 
R

RickD

You can track time against non-billable and bilable tasks but it leverages
basic MS Project functionality. Resources will have to have a zero rate in
Standard Rate "B". All billable tasks use the default Standard Rate "A" and
any non-billable tasks use Table "B". A PM has to set this up. From a
timesheet perspective, one would have to use task naming conventions for
resources to be able to determine billable versus non-billable tasks. Not
elegant perhaps but it works.
 