I work for a VAR and we are working on implementation of Project Server. The
organization would like to use Project Server to manage engagements.
Although I understand the standard rate and overtime rates just fine, I am
having an issue with the following scenario:
Same resource
2 different engagements
2 different rates for the resource on the engagements
Both engagements are running concurrent
I can edit the resource and update the standard rate, which changes the rate
across the enterprise. However, I cannot change the rate on the resource
sheet just for that individual project (error message comes up stating that
the rate can be changed for modeling purposes only and will be overwritten
the next time it is opened).
Please advise as to a solution for this occurrence.
organization would like to use Project Server to manage engagements.
Although I understand the standard rate and overtime rates just fine, I am
having an issue with the following scenario:
Same resource
2 different engagements
2 different rates for the resource on the engagements
Both engagements are running concurrent
I can edit the resource and update the standard rate, which changes the rate
across the enterprise. However, I cannot change the rate on the resource
sheet just for that individual project (error message comes up stating that
the rate can be changed for modeling purposes only and will be overwritten
the next time it is opened).
Please advise as to a solution for this occurrence.