Hello Andy,
Welcome to this Microsoft Project General Questions newsgroup, and thank you
for your honesty in pointing out that you are a new user of this fascinating
application.
With this said, I'll try to make my answer as simple as I can: Every project
must have start and finish dates, therefore, all its tasks must have them too.
When you create a new project in Microsoft Office Project, many things
happen in the background that are set as default, two of them are: the
scheduling method (default: Project start date), and the project's calendar
(default: Standard).
Since the Project start date is set as the default scheduling method, a
Project Start Date is also set, using the project's creation date.
Now, when you type a name in the first row of the column "Task Name", some
other things happen by default: A task duration is set as 1 day, that
duration is represented with a bar in the Gantt chart, and of course, start
and finish dates for the task are set based on its duration. But also a
constraint type (as soon as possible) is set by default. This means that,
without any task dependencies established, the task will start at project's
start date.
I surely hope this can be useful to you and I do recommend you to follow
Mike Glen's advise, but I would like to add a couple of links from Project
2007 On-line Help for you:
http://office.microsoft.com/en-us/project/HA102354821033.aspx
and
http://office.microsoft.com/en-us/project/HA102130271033.aspx
Please, let us know how you come along.