You can do it but it might defy logic to do so. The FS link says there is
some physical process that makes it mandatory for the predecessor to finish
before the successor is able to begin. The successor may start LATER than
the link allows but it is impossible for it to start earlier. So if you need
to have the sucessor stay in its place when the predeccor finishes earlier
than planned, that's okay and a SNET or FNET constraint on the sucessor will
do that for you. But to not allow it to push the sucessor out if the
predecessor finishes later than planned does not make any sense.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
MS MVP
assaf1978 said:
Hi,
Is it possible for 2 activities to be connected (using standard FS
connection) and for the predecessor to be updated (finish date changed),
without the succecssor changing at all ?
Thanks,
Assaf.