D
Dale Howard [MVP]
Naomi --
First of all, understand that Percent Complete is not an estimate. It is a
calculated as Actual Duration/Duration * 100. The trick is to figure out
how the system calculates Actual Duration, which is not obvious. Consider
the following scenario:
1. The first task in a four-task project has a 5-day Duration with three
resources assigned.
2. Two of the resources submit their % Work Complete as 100%.
3. The third resource has not reported yet, so his % Work Complete is 0%.
4. I have three other tasks in the project, each with a 5-day Duration,
linked with FS dependencies, and the tasks have not started yet.
5. The Duration of the entire project is 20 days.
The Duration of the task is 5 days. Actual Duration is calculated as
Duration * Percent Complete. In my scenario above, Microsoft Project
calculates the Percent Complete value as the average of the % Complete for
the three resources reporting on the task. The % Complete, therefore, is
(100% + 100% + 0%)/3 = 200%/3 = 66.67%. The system then calculates Actual
Duration for the task as 5d * 66.67% = 3.33 days.
When the system calculates the % Complete for the entire project, it factors
in the % Complete for each task, calculated using the information presented
above. So, in my example above, the Actual Duration for the project matches
the Actual Duration for the first task, which is 3.33 days. The system
calculates the % Complete for the entire project as 3.33/20 * 100 = 17%.
It's not an easy concept to understand how Project calculates % Complete,
but believe me, it is not an estimate. It is a calculated number. To learn
more about how Microsoft Project calculates % Complete, read the Help
articles on the % Complete column and the Actual Duration column. Hope this
helps.
First of all, understand that Percent Complete is not an estimate. It is a
calculated as Actual Duration/Duration * 100. The trick is to figure out
how the system calculates Actual Duration, which is not obvious. Consider
the following scenario:
1. The first task in a four-task project has a 5-day Duration with three
resources assigned.
2. Two of the resources submit their % Work Complete as 100%.
3. The third resource has not reported yet, so his % Work Complete is 0%.
4. I have three other tasks in the project, each with a 5-day Duration,
linked with FS dependencies, and the tasks have not started yet.
5. The Duration of the entire project is 20 days.
The Duration of the task is 5 days. Actual Duration is calculated as
Duration * Percent Complete. In my scenario above, Microsoft Project
calculates the Percent Complete value as the average of the % Complete for
the three resources reporting on the task. The % Complete, therefore, is
(100% + 100% + 0%)/3 = 200%/3 = 66.67%. The system then calculates Actual
Duration for the task as 5d * 66.67% = 3.33 days.
When the system calculates the % Complete for the entire project, it factors
in the % Complete for each task, calculated using the information presented
above. So, in my example above, the Actual Duration for the project matches
the Actual Duration for the first task, which is 3.33 days. The system
calculates the % Complete for the entire project as 3.33/20 * 100 = 17%.
It's not an easy concept to understand how Project calculates % Complete,
but believe me, it is not an estimate. It is a calculated number. To learn
more about how Microsoft Project calculates % Complete, read the Help
articles on the % Complete column and the Actual Duration column. Hope this
helps.