C
Carla
How can we use project to constrain a task based on availability of a room or
equipment, but not be required to enter hours for that room or equipment? For
example, let's say we have a meeting room that is unavailable the first week
of every month. When the project reaches a task that requires that room, I
want the task to be bumped out to the following week when the room is
available. Right now we have added the room as a resource on that task, but
that requires us to enter time against the room in order to mark the task
100% complete. (If I enter the room with zero hours required, then it doesn't
bump the schedule since the room doesn't have any work assigned.) We're using
project 2003. Thanks in advance for your suggestions.
equipment, but not be required to enter hours for that room or equipment? For
example, let's say we have a meeting room that is unavailable the first week
of every month. When the project reaches a task that requires that room, I
want the task to be bumped out to the following week when the room is
available. Right now we have added the room as a resource on that task, but
that requires us to enter time against the room in order to mark the task
100% complete. (If I enter the room with zero hours required, then it doesn't
bump the schedule since the room doesn't have any work assigned.) We're using
project 2003. Thanks in advance for your suggestions.