Environment: Project Server 2003 with SP1.
I facing this resource booking type problem.
1. I created a new project plan
2. Went to build team from enterprise
3. under Group By drop down selected RBS
4. Added resources under my RBS tree
5 On the Project team resource windows on right, the booking type of few
resources gets changes to 'Proposed'. (this is happening for few teams)
See the screenshots:
http://tinypic.com/eahan9.jpg
http://tinypic.com/eahao6.jpg
I've confirmed the booking type of those resource as committed in resource
information window of those users. If I don't select RBS in group by drop
down & directly add that resource, then their booking type is correct.
This issue causes problem as few managers expect every thing good where as
the booking type of proposed doesn't get the tasks in their timesheet.
Why the booking type gets changed to proposed?
Any clue?
I facing this resource booking type problem.
1. I created a new project plan
2. Went to build team from enterprise
3. under Group By drop down selected RBS
4. Added resources under my RBS tree
5 On the Project team resource windows on right, the booking type of few
resources gets changes to 'Proposed'. (this is happening for few teams)
See the screenshots:
http://tinypic.com/eahan9.jpg
http://tinypic.com/eahao6.jpg
I've confirmed the booking type of those resource as committed in resource
information window of those users. If I don't select RBS in group by drop
down & directly add that resource, then their booking type is correct.
This issue causes problem as few managers expect every thing good where as
the booking type of proposed doesn't get the tasks in their timesheet.
Why the booking type gets changed to proposed?
Any clue?