Booking type per Project sharing ressources

F

Franck

Hi,

I would like to know how/if booking type can be set by project or even by
task instead of the entire resource only?

Example:
- project0 contains the shared resource pool containing resource1 and
resource2
- project1 contains task1, and uses shared resource pool from project0
- project2 contains task2 and task3, and uses shared resource pool from
project0

I would like to do so that:
- resource1 has booking type set to confirmed on task1 of project1 &
- resource1 has booking type set to confirmed on task1 of project2
or
- resource1 has booking type set to confirmed on task2 of project2 &
- resource1 has booking type set to confirmed on task3 of project2

But I can only change booking type at resource level (so it impacts all
projects and tasks). Any idea?
I have read it should be possible at least per project, but I dont seem to
manage to lake it work. Would it require resources to be defined on Project
Server?

Thanks,
Franck
 
D

Dale Howard [MVP]

Franck --

Booking Type is a field used in conjunction with Project Server and can be
set for each resource on a project by project basis if you use Project
Server. Hope this helps.
 