Booking Type - Propose & Committe

N

Ng

HI all,

I saw the below information about Booking Type In microsoft project 2003.
"Note that a resource's booking type applies to all their assignments in the
project"

So may i know have any way, so i can set the resource booking type like this.
example:
if i have a project has 3 task. and today date is 15/oct/2005
task 1 - 01/oct/2005 - 9/oct/2005 - resourceA (committed)
task 2 - 10/oct/2005 - 19/oct/2005 - resourceA (committed)
task 3 - 20/oct/2005 - 30/oct/2005 - resourceA (Propose)



Thanks,
Ng
 
G

Gary L. Chefetz [MVP]

Ng:

Are you asking whether the statement you're quoting is incorrect? If so, the
answer is that booking type applies at the project level, not the task
level.
 
N

Ng

Gary ,

So in the same project, each resources booking type only can either Committe
or Propose.
ok, i understand now.

Thank you.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top