HI all,
I saw the below information about Booking Type In microsoft project 2003.
"Note that a resource's booking type applies to all their assignments in the
project"
So may i know have any way, so i can set the resource booking type like this.
example:
if i have a project has 3 task. and today date is 15/oct/2005
task 1 - 01/oct/2005 - 9/oct/2005 - resourceA (committed)
task 2 - 10/oct/2005 - 19/oct/2005 - resourceA (committed)
task 3 - 20/oct/2005 - 30/oct/2005 - resourceA (Propose)
Thanks,
Ng
I saw the below information about Booking Type In microsoft project 2003.
"Note that a resource's booking type applies to all their assignments in the
project"
So may i know have any way, so i can set the resource booking type like this.
example:
if i have a project has 3 task. and today date is 15/oct/2005
task 1 - 01/oct/2005 - 9/oct/2005 - resourceA (committed)
task 2 - 10/oct/2005 - 19/oct/2005 - resourceA (committed)
task 3 - 20/oct/2005 - 30/oct/2005 - resourceA (Propose)
Thanks,
Ng