Booking Type - Propose resource

N

Ng

hi all,

i have a question about booking type.
example:
if i have a project has 3 task. and today date is 15/oct/2005
task 1 - 01/oct/2005 - 9/oct/2005 - resourceA
task 2 - 10/oct/2005 - 19/oct/2005 - resourceA
task 3 - 20/oct/2005 - 30/oct/2005 - resourceA

how can set the task 3 - resourceA booking type is propose resource
until today date is equal task 3 start date, then the resourceA will change
to committe resource.

Thanks,
Ng
 
D

Dale Howard [MVP]

Ng --

In the future, please post your Project Server questions to the
microsoft.public.project.server newsgroup, as this newsgroup is devoted to
the Microsoft Project desktop application only. To answer your question,
you can't. You will need to manually change the Booking type from Proposed
to Committed. Hope this helps.
 
N

Ng

Dale Howard ,
Sorry, next time i wll post Project Server questions to the
microsoft.public.project.server newsgroup.

I think my question have some problem.
I see the below information in microsoft project 2003
"Note that a resource's booking type applies to all their assignments in the
project"

So may i know have any way can set the resource booking type like this.
example:
if i have a project has 3 task. and today date is 15/oct/2005
task 1 - 01/oct/2005 - 9/oct/2005 - resourceA (committed)
task 2 - 10/oct/2005 - 19/oct/2005 - resourceA (committed)
task 3 - 20/oct/2005 - 30/oct/2005 - resourceA (Propose)

I will post my question to microsoft.public.project.server newsgroup.

Thanks,
Ng
 