F
Frederick
Good day, we are using MSP2003 SP2-A.
Question: if an enterprise resource has actual work (previously entered via
PWA and approved into the project plan) and the state of the resource's
booking type is changed to "proposed" in the project plan, would the actual
work appear in the Portfolio Analyzer OLAP Cube?
Documentation I have seen "seems" to indicate that it should appear,
however, tests have shown varying responses (sometimes it does, sometimes it
doesn't appear).
Much appreciate your input!
Question: if an enterprise resource has actual work (previously entered via
PWA and approved into the project plan) and the state of the resource's
booking type is changed to "proposed" in the project plan, would the actual
work appear in the Portfolio Analyzer OLAP Cube?
Documentation I have seen "seems" to indicate that it should appear,
however, tests have shown varying responses (sometimes it does, sometimes it
doesn't appear).
Much appreciate your input!