S
Silene
If there is a break of e.g. 1 week at some point in a project that nobody in
working in it for any reason, how do I link the finish-start dates? Is it
right just to fix the dates or I write a task saying 'break time' = 1 weeek?
I wouldnt like this week to count in the duration of the project?
I hope I explain myself!
Thanks
Silene
working in it for any reason, how do I link the finish-start dates? Is it
right just to fix the dates or I write a task saying 'break time' = 1 weeek?
I wouldnt like this week to count in the duration of the project?
I hope I explain myself!
Thanks
Silene