P
paul
Let's say I have a task that is estimated to take 8 wks in a baselined
schedule. Actual work is recorded as it occurs, but it becomes
apparent that estimating the remaining effort is tough for such a
large task. I'd now like to break this task up into several subtasks
for easier tracking, resource coordination, etc. If I were smart, I
would have done this at the outset -- but I wasn't.
What can be done to break this task up AND keep (recreate?) the
baseline and actual work information?
schedule. Actual work is recorded as it occurs, but it becomes
apparent that estimating the remaining effort is tough for such a
large task. I'd now like to break this task up into several subtasks
for easier tracking, resource coordination, etc. If I were smart, I
would have done this at the outset -- but I wasn't.
What can be done to break this task up AND keep (recreate?) the
baseline and actual work information?