Spunky
MS Project 2003 enterprise. I have a master schedule with 50 + projects.
The number varies from week to week, some projects drop off, others are
added. What is the quickest way to break the links each week? For now I
open the task information for each one and uncheck the linked box. I'm sure
there is VB code that would do this for the entire project regardless of
number of projects. I know some VB but not enough to do this. Thank You.