S
Sinister
I have a bit of a problem with 2007. I work in an environment where it's
crucial to be able to track tasks that don't have an end date. We call them
bucket tasks. For example, SERVER MAINTENANCE or MEETINGS - FOR PROJECT X.
The way we were doing these in 2003 was to make the task a fixed duration -
not effort driven. Then we assign the resources and remove any hours they had
assigned from the work field. When they needed to put time against these type
of tasks they would go into their tasks in PWA 2003, make sure "All Tasks"
was selected, and put in the time they worked.
I've noticed 2007 has removed the "All Tasks" option from PWA, and now a
user can only see current tasks. Because these tasks are always listed as
complete there doesn't seem to be a way to show them.
Some have suggested using the administrative time section in PWA but it
doesn't let me select who can see what admin task.
Help! This is kind of a make or break situation here. If I can't figure out
a way to capture these type of tasks the management has talked about
switching to another product.
Any help on this is much appreciated.
crucial to be able to track tasks that don't have an end date. We call them
bucket tasks. For example, SERVER MAINTENANCE or MEETINGS - FOR PROJECT X.
The way we were doing these in 2003 was to make the task a fixed duration -
not effort driven. Then we assign the resources and remove any hours they had
assigned from the work field. When they needed to put time against these type
of tasks they would go into their tasks in PWA 2003, make sure "All Tasks"
was selected, and put in the time they worked.
I've noticed 2007 has removed the "All Tasks" option from PWA, and now a
user can only see current tasks. Because these tasks are always listed as
complete there doesn't seem to be a way to show them.
Some have suggested using the administrative time section in PWA but it
doesn't let me select who can see what admin task.
Help! This is kind of a make or break situation here. If I can't figure out
a way to capture these type of tasks the management has talked about
switching to another product.
Any help on this is much appreciated.