C
Christine Pouliot
I have two questions related to entering realistic
budgeted costs into our project.
1. We have internal resources used on the project where
the cost is their loaded salary times duration on the
project, regardless of hours booked against the project.
I've seen the ability to put a fixed cost per use, but
what I really need is a fixed cost per resource per week.
Is there a way I can record this in project?
2. I also want to budget time at a summary task, and have
resources record time at a detail task level. Is this
possible. The example is a task that will last the
duration of the project like - rollout support for 440
days, but I want to track hours at more detailed level,
for example I have 2 staff and they will perform tasks,
like model management, design review, functional testing.
I don't really want to try to guess an allocation to these
detail tasks if I can avoid it. Any ideas?
Thanks,
budgeted costs into our project.
1. We have internal resources used on the project where
the cost is their loaded salary times duration on the
project, regardless of hours booked against the project.
I've seen the ability to put a fixed cost per use, but
what I really need is a fixed cost per resource per week.
Is there a way I can record this in project?
2. I also want to budget time at a summary task, and have
resources record time at a detail task level. Is this
possible. The example is a task that will last the
duration of the project like - rollout support for 440
days, but I want to track hours at more detailed level,
for example I have 2 staff and they will perform tasks,
like model management, design review, functional testing.
I don't really want to try to guess an allocation to these
detail tasks if I can avoid it. Any ideas?
Thanks,