R
rsmithgi
I have written a macro that calculates the burdened cost (stored in cost10)
of tasks by summing the burdened cost for each resource assigned to the task.
In addition, I'd like the burdened cost for each assignment to be saved as
well (in the cost10 assignment field). Ultimately, I want to output (to
excel) as spreadsheet that looks like the table section of the task usage and
resource usage views.
When I store the burdened cost in the task assignment.cost10 field, the value
does not appear in the task usage display. I am also storing burdened cost
values in the resource assignment.cost10 field. The burdened costs do appear
properly in the resource usage view.
I tried the macro in Project 2003 (I removed the use of resource
assignment.cost10 field) and the macro works fine.
Have I run into something in Project 2007?
of tasks by summing the burdened cost for each resource assigned to the task.
In addition, I'd like the burdened cost for each assignment to be saved as
well (in the cost10 assignment field). Ultimately, I want to output (to
excel) as spreadsheet that looks like the table section of the task usage and
resource usage views.
When I store the burdened cost in the task assignment.cost10 field, the value
does not appear in the task usage display. I am also storing burdened cost
values in the resource assignment.cost10 field. The burdened costs do appear
properly in the resource usage view.
I tried the macro in Project 2003 (I removed the use of resource
assignment.cost10 field) and the macro works fine.
Have I run into something in Project 2007?