Hello,
What is/are the parameter(s) which manage the availability of the resources
in the Build Team dialog for a specific Project Manager.
I didn't activate any filter.
Some resources are greyed out while they have many hours available
and they are in the same branch of the RBS than Project Manager
Some resources are *not* greyed out so the Project Manager can choose them
while they are in another branch of the RBS.
Thanks for help
What is/are the parameter(s) which manage the availability of the resources
in the Build Team dialog for a specific Project Manager.
I didn't activate any filter.
Some resources are greyed out while they have many hours available
and they are in the same branch of the RBS than Project Manager
Some resources are *not* greyed out so the Project Manager can choose them
while they are in another branch of the RBS.
Thanks for help