H
Hart
Want to status a task and have Project recalculate work
based on percent complete of original budget without
recalculating duration. For example, I'd like to status
a 10-day, (100) hour task at 50% and fix the remaining
duration at 7-days (will now be an twelve day total
duration as the original estimate may have been
incorrect) and find (50) remaining hours of work
(REGARDLESS OF RESOURCES/UNITS ASSIGNED). Possible, easy
adjustment?
based on percent complete of original budget without
recalculating duration. For example, I'd like to status
a 10-day, (100) hour task at 50% and fix the remaining
duration at 7-days (will now be an twelve day total
duration as the original estimate may have been
incorrect) and find (50) remaining hours of work
(REGARDLESS OF RESOURCES/UNITS ASSIGNED). Possible, easy
adjustment?