I'm using MS Project as the interface to CA's Clarity PM software. It works
okay but I'm having trouble saving baseline information - I can establish a
baseline in MS Project, save the plan to Clarity, but when I re-open the
plan, the baseline info is not in the project plan. Any ideas?

Paul C. Peterson
Velox Consulting, LLC
 
J

Jack Dahlgren MVP

Try importing once. Save that as a baseline, then import again on top of it
with current data?

-Jack

"Paul Peterson - Velox Consulting, LLC"
 
J

Jan De Messemaeker

Hi,

This is a Clarity setting, that only some high authority can set a baseline
VIA CLARITY and that Project's baselines are simply not taken into account.
Check with your Clarity administrator

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Paul Peterson - Velox Consulting, LLC"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top